Ba Ria – Vung Tau: Spend more than VND444 billion to build public park


Ba Ria – Vung Tau People’s Committee has approved the construction drawing design, total cost estimate construction Ba Ria Park (phase 2), Phuoc Nguyen Ward, Ba Ria.

Accordingly, the total construction cost of the second phase is more than VND225 billion (while the first phase is more than VND218 billion).

Ba Ria Park project was approved by the People’s Committee of Ba Ria-Vung Tau Province from October 2013, funded by the State Budget, Ba Ria is the investor. The park covers an area of ​​44.6 hectares, divided into two phases.

A corner of Ba Ria Park Square has been built

A corner of Ba Ria Park Square has been built

The park will have the following items: Square area of ​​7.2ha (including square, stage, car park, low density lawn mixed grass); 28.68 ha of forest park (grass area, lake, artificial hill, operating area, hut, car park …); roads, technical infrastructure …

The phase of a Ba Ria Park project will be built within three years. It is expected that when construction is completed, there will be the square of 20,000 people; The two-storey building has an area of ​​1,367 square meters and features functional rooms such as conference rooms, conference rooms, sound and light rooms, storage facilities, central lounge area, lobby , Covered; Lighting system, power supply, drainage …

Phase two of the project is expected to include the following items: Operator, six huts, benches, five entrances to the park, guardhouse, fence; four toilets, roads; flower frame, flower tower; six fountains; green trees; light; water supply

In early July 2018, after being approved by the provincial People’s Committee, Ba Ria has also approved the design adjustment, cost estimate of Ba Ria Park (phase 2), assigned the project management unit of construction 1, Ba Ria city is the representative of the project owner who is responsible for coordinating with other organizations to implement the project.

In fact, in Ba Ria city also has many other small and medium parks. However, the Ba Ria Park project is expected to meet the needs of people for recreation, sports, relaxation; In addition, the investment of large square in the park to organize events, festivals of Ba Ria – Vung Tau and Ho Chi Minh City (administrative center of Ba Ria – Vung Tau province).

After the completion of phase one, Ba Ria Park is now near the completion of the square, surrounding streets but not as planned. Many items are being leveled up and continue to be implemented. Recently, some cultural events of Ba Ria – Vung Tau Province were held in the square, because there is no ceremony, the organizers temporarily arranged seats, set up outdoor stage.

You are reading the article Ba Ria – Vung Tau: Spend more than VND444 billion to build public park in the Real Estate category at https://realestatevietnam.com.vn/.Any information sharing, feedback please email to contact.vietnamrealestate@gmail.com, Hotline (+84) 898 898 688 (24/7).

Special thanks!

Đánh giá bài viết

Related Posts
  • VINHOMES GRAND PARK VINHOMES GRAND PARK
    The Vinhomes Grand Park project in District 9 (Thu Duc City) is a mega-urban park of the investor...
  • THE CENTENNIAL BA SON
    Situated in a golden location at No.2 Ton Duc Thang Street, Distric 1, HCMC. The Centennial is...
  • SONASEA VILLAS AND RESORT PROJECT
    Located in Duong To ward, Phu Quoc district, Kien Giang Province, Sonasea Villas & Resort is a...