Close Metro Number 1 Hundreds Of Million Dollar Gliders In The Air, About To Mount Rail In Saigon

Urban railway No. 1

Urban railway No. 1 (Ben Thanh – Suoi Tien) will be installed rails, Rach Chiec bridge – Ha Noi Highway on October 23rd.

Urban railway No. 1 (Ben Thanh – Suoi Tien) is 19.7 km long (including 2.6 km underground and 17.1 km on high). There are 14 terminals (3 underground stations and 11 elevated stations) with the total investment capital of $2.2 billion, expected to be completed and put into operation by the end of 2020.

The project has implemented 3 construction contracts and 1 procurement contract in the form of EPC contract.

Urban railway No. 1
This route is 19.7 km long (including 2.6 km underground and 17.1 km high) with a total investment of VND47.325 billion

Accordingly, the CP1 package includes underground construction from the Ba Son-Nghe An railway station, which is under construction by the subcontractor contractor Shimizu – Maeda, which has excavated 700m / 781m underground, depth 17m (average 10m / day), expected completion by the end of 10/2017. After the TBM drilling machine completes the section from Ba Son station to the Opera House, it will move all the equipment back to Ba Son station for construction of the second tube to the 190m theater, at a depth of 27m;

Underground construction from Ben Thanh station – City Theater station, contractor Sumitomo Misui – Cienco4 construction, has completed the geological survey of the area and continued to perform in the coming time.

For CP2 package: high urban railway linking Ba Son (Ben Nghe Ward, District 1) along Nguyen Huu Canh Street, crossing the Saigon Bridge running along the Hanoi Highway to the Long Binh (Long Binh Ward, District 9), has completed 100% of bored piles, pillars, cylinders, castings beam, U beam (360 spans).

Along the urban railway, it has 5 special bridges, the contractors have matched three bridges: Van Thanh, Saigon, Rach Chiec. The remaining bridge is overpass Hanoi Highway and Dien Bien Phu, reaching 50% of the project.

Urban metro system No.1 includes 14 stations: Van Thanh, Thao Dien, Phuoc Long, Rach Chiec, Binh Thai, High Tech Park, National University, Thu Duc, An Phu, Tan Cang, now reaching 80% of the works. The terminal (Long Binh Ward, District 9) constructed the main drainage system, workshop and parking lot 62%.

Urban railway No. 1
On October 23rd, the urban railway from Rach Chiec Bridge – Ha Noi’s Overpass will be fitted with the first rail rails

In addition, CP3 package: procurement of electromechanical equipment, locomotives, rails and maintenance, manufactured by Hitachi (Japan). Expected on October 23rd, the urban railway No. 1 will be installed ray from Rach Chiec Bridge to the flyover of Hanoi Highway. By 8/2018, the first metro trains were transported to Vietnam.

CP4 Bidding Package: IT system for the office and the O & M company plans to launch the 2018 technical design.

Urban railway No. 1
Overview of urban railway No. 1, viewed from above the pass through Thao Dien area (District 2, Ho Chi Minh City)

As noted, the urban railway No. 1, from Long Binh terminals (District 9) to the Ba Son station (Ben Nghe Ward, District 1) construction of the remaining 4 points is not linked to Ha Noi Highway (Linh Trung Ward, Thu Duc District), Thu Duc crossroads (Binh Tho Ward, Thu Duc District), via Vincom Mega Mall Thao Dien (Thảo Điền street, District 2) and the foot of Sai Gon bridge borders Dien Bien Phu street (P.22, Binh Thanh district).

Along the urban railway No. 1 (section of the High-Tech Park – Rach Chiec bridge) the rail surface was completed the whole rough, ready to install the rails on October 23rd.

Urban railway No. 1
Metropolitan railroad No. 1 on high, everything is ready and ready to mount the rails

You can read more information at Vietnam Real Estate News

The representative of the HCMC Railway Administration said that in 2006, the estimated cost of urban railway No.1 was estimated at $773 million. In 2008, the project was approved by the Government, with the support of the Japanese consulting firm with a total investment experience of $214 million, which is close to reality.

The above cost, the City People’s Committee has invited evaluation units of Singapore, then consulted and approved by many ministries and the Prime Minister.

Urban railway No. 1
Bidders have three bridges: Van Thanh, Saigon, Rach Chiec. The remaining bridge is overpass Hanoi Highway and Dien Bien Phu 50% of the project

However, according to the management of urban railway, the urban railway projects in the city are facing the risk of lack of money. The demand for ODA capital for the whole metro line 1 for 2017 is $246 million, but by April 2017, the central government allocated only $91 million.

Since there is no money paid for workers on Lunar New Year 2017, the Board has applied for $27.3 million. Recently, the City People’s Committee has continued to pay $23 million to pay for the contractor. However, even the additional $23 million is not enough demand because each month the value needs to pay the contractor about 23 – 27.5 million.

Therefore, the CMU hopes the ministries and branches to pay attention not only to the metro line 1 but also to the city to invest in urban infrastructure, socio-economic development, ensuring the projects are implemented properly.

Urban railway No. 1
Urban railway pass through residential area P.22 Binh Thanh District, connecting Ba Son Station (Ben Nghe Ward, District 1)
Urban railway No. 1
Inside the high-tech park, 80% of the works have been completed
Urban railway No. 1
As noted by Thanh Nien, there are four unconnected points, including the following points: Ha Noi Highway overpass (Linh Trung Ward, Thu Duc District), Thu Duc crossroad crossing (P. Binh Thuc District, Thu Duc District, via Vincom Mega Mall Thao Dien (Thao Dien Ward, District 2) and Sai Gon Bridge crossing Dien Bien Phu Street (P.22, Binh Thanh District)
Urban railway No. 1
An elevated urban railway running along the Hanoi Highway (District 9, Ho Chi Minh City)

You are reading the article “Close Metro Number 1 Hundreds Of Million Dollar Gliders In The Air, About To Mount Rail In Saigon” in the Real Estate category at https://realestatevietnam.com.vn/. Any information sharing, feedback please email to info@realestatevietnam.com.vn, Hotline 0909890897 (24/7).
Special thanks!

Close Metro Number 1 Hundreds Of Million Dollar Gliders In The Air, About To Mount Rail In Saigon
Review

Comments (0)