It took half a year to restart the tide-building works of 10,000 billion


Many engineers and workers at the tidal block project have quit their job. The staff of the project from 2,200 people has reduced to 400 people …

Trung Nam BT 1547 Co., Ltd – the implementing unit for flood relief for HCMC (total funding of nearly VND10 trillion), has continued to petition the People’s Committee of Ho Chi Minh City to solve problems related to This project has to stop construction for a long time, the construction time has not yet been determined.

According to Trung Nam BT 1547, at present, engineers and workers leave a lot. The staff of the project from 2,200 people has reduced to 400 people to maintain, waiting for procedures disbursement of the project funds … Therefore, if the problems of the project are resolved smoothly, to restart work construction takes about six months.

Trung Nam BT 1547 said that besides difficulties due to the lack of funds for construction, the ground for construction has not been fully handed over (as promised in the contract completed in the month). 5-2018).

The tide control works have stopped construction nearly 3 months

The tide control works have stopped construction nearly 3 months, has not specified the construction time back.

For the above reasons, Trung Nam BT 1547 said that it is unlikely that the project will be completed on schedule, ending in mid-2019 as the contract signed.

As the Ho Chi Minh City Law has informed, in the beginning of May 2018, Trung Nam BT 1547 suddenly announced the stop construction works in the project against flooding tide for Ho Chi Minh City.

Trung Nam BT 1547 said that the reason for stopping the construction was that the Bank for Investment and Development of Vietnam (BIDV) – Sai Gon Branch stopped disbursing the project. Pending the above procedures, due to lack of capital mobilized, the Company ceased construction.

According to Trung Nam BT 1547, the works under the tide control project to stop construction in addition to the risk of causing unsafety to waterway traffic is potentially dangerous to nearby works, especially the house. .

You are reading the article It took half a year to restart the tide-building works of 10,000 billion in the Real Estate category at https://realestatevietnam.com.vn/.Any information sharing, feedback please email to contact.vietnamrealestate@gmail.com, Hotline (+84) 898 898 688 (24/7).

Special thanks!

Đánh giá bài viết

Related Posts
  • VINHOMES GRAND PARK VINHOMES GRAND PARK
    The Vinhomes Grand Park project in District 9 (Thu Duc City) is a mega-urban park of the investor...
  • THE CENTENNIAL BA SON
    Situated in a golden location at No.2 Ton Duc Thang Street, Distric 1, HCMC. The Centennial is...
  • SONASEA VILLAS AND RESORT PROJECT
    Located in Duong To ward, Phu Quoc district, Kien Giang Province, Sonasea Villas & Resort is a...