(+84) 898 898 688After three months of issuing Decision No. 60/2017 of the City People’s Committee stipulating the minimum area to be separated in the city, Mr. Nguyen Thanh Toan, Deputy Director of the Department of Planning and Investment, Districts on technical infrastructure conditions and pre-acceptance test of technical infrastructure systems in case of separation of land plots with the formation of traffic roads and technical infrastructures under this Decision.
According to the Department of Planning and Investment, the land can only be split up after the land user completes the technical infrastructure and is accepted by the functional agency.
According to Decision 60, for land parcels formed roads and technical infrastructure, the City People’s Committee directed the People’s Committee of the district must set up inter-branch working group to consider and solve. Guiding documents of the Department of Planning and Investment clarify the responsibility of localities to develop a specific plan for each year, evaluate the report on biannual results in the separation of roads formed roads .
The separation of this plot must be based on the specific plan of each district in the year and based on the zoning plan of 1/2000 scale, detail plan of the rural population.
At this point, the Department of Planning and Investment of the district has to identify the areas planned for the existing residential land, residential land combined with embellishment, including newly built residential land, land use Use the mixture of functions in separate cases under Decision 60, urgently detailed planning 1/500 scale. This is to “serve as the basis for urban management in accordance with the approved plan for the separation of land parcels in combination with urban refurbishment in the area” – the document of Planning – Economic Department .
After planning the 1/500 master plan, the district office will hold an inter-branch working group meeting to consider and agree on the technical infrastructure investment plan for the land areas with the need to separate land plots.
According to Planning – Economic Department, as the basis for the separation of land parcel to ensure synchronous technical infrastructure and social infrastructure in accordance with the planning, district People’s Committee urgently need to develop the plan To elaborate the detailed planning on the construction of the scale of 1/500 of the planned land plots as described above. At least in the second quarter of 2018, the district must send this plan to Planning and Investment Department for coordinated implementation.
“Pending the preparation, appraisal and approval of detailed planning with the scale of 1/500, the cases of separating the land form roads and technical infrastructure, the district will get the written agreement. of the Department of Planning and Investment on planning before approving the land allocation. The Department will give written opinions at least 15 working days from the date of receiving the official letter of the district.
In the guideline document, Planning and Investment Department has specific criteria for internal traffic, elevation and surface water drainage, water supply and drainage, electricity supply, lighting and communication. into a road.
According to Planning and Investment Department , the new road will be built according to the 1/2000 master plan or approved rural residential area planning. If at least 12m from the road, the width of the road must be at least 7m, the pavement must not be less than 1m, the roadbed must not be less than 4m.
New guidelines on land parcel separation in Ho Chi Minh City
For new traffic roads connected with alleys and roads planned with a road limit of 7 m or less, newly-built roads shall not be smaller than the approved plannings. Where the alley road has a road width of more than 7 m and less than 12 m, then the new traffic road shall not be smaller than 7 m.
For areas without alley road planning, the new road widths must comply with Decision No. 88/2007 of the City People’s Committee stipulating the road and road management in existing residential areas.
If newly formed roads affect adjacent households, according to the Department of Planning and Investment, land users must cooperate with People’s Committee of ward / commune to get opinions of affected households before proposing. Agreement on investment in technical infrastructure.
~~>>Update on new information on the real estate news in Vietnam here: Vietnam real estate news
– To invest in the construction of the technical infrastructure system according to the approved plan. To strictly follow the connection of power supply, water supply, drainage and solid waste treatment.
– To compile the dossier on completion of works and organize the takeover.
– Make list of construction completion documents.
– Warranty works according to regulations. The warranty period is from the signing date of the minutes of technical infrastructure transfer and not less than 12 months.